×

ODOT project updates for Columbiana County

NEW PHILADELPHIA – The following construction projects are anticipated to affect highways in Columbiana County in the coming weeks. All outlined work is weather permitting.

U.S.Route 30 (Lincoln Way) traffic signal upgrade: Project includes signal upgrades at the intersections of U.S. 30 (Lincoln Way) with SR 45/SR 154, Beaver Street, Market Street, and Jefferson Street. Completion date is Oct. 31.

U.S. Route 30 resurfacing project: Resurfacing of U.S. Route 30 from SR 7/SR 267 to SR 170. During this work, one lane of traffic will be maintained in each direction. Completion date is Oct. 31.

State Route 11 resurfacing project: Project includes the resurfacing of SR 11 from the Columbiana/Mahoning County line to just south of the SR 344 interchange. During this work one 11-foot lane of traffic maintained. Completion date is Sept. 30.

SR 7 bridge replacement: located east of Columbiana between SR 14 and Metz Road. Traffic maintained via temporary traffic signals. Completion date is June 30, 2021.

Safety project in East Palestine: Project includes the installation of pavement markings, traffic signal upgrades, and pedestrian signal upgrades. Traffic maintained via flaggers when necessary. Completion date is Sept. 30.

Multiple Columbiana County routes to be resurfaced: Project includes the resurfacing of SR 45 in Salem from Township Road 410 to U.S. Route 62, SR 558 from SR 45 to SR 517, and SR 9 from the Carroll/Columbiana County line to U.S. Route 30. Completion date is Nov. 30.

NEWSLETTER

Today's breaking news and more in your inbox

I'm interested in (please check all that apply)
   

Starting at $4.39/week.

Subscribe Today