Salem water department to seek bids for water line at new school
Trending
SALEM -- The utilities department will seek bids for the installation of a new water line to the Salem City School District's new K-8 school building.
City council Tuesday voted to approve an ordinance authorizing the utilities department to advertise for bids and enter into contracts for the installation of a 12-inch main water line for the new school building.
Utilities Superintendent Chad Hess said the line would be more than 2,000 feet long in total and begin on Pershing Street near Giant Eagle, joining with the school's existing lines on Merle Road.
Hess said that the city and the school district will be splitting the costs of engineering for the project and the installation of the main line down the middle. However, the city will cover the full cost of connecting dead end streets along the route to the new line to maintain water flow.
Hess also said that the Ohio Environmental Protection Agency had given its approval for the project and that it was on schedule to begin construction in March.
During its recent meeting on Nov. 9, the Salem school board approved an agreement between the school district and the city to share the construction costs for the project as part of its consent agenda. At that meeting Treasurer Mike Douglas said that the line was necessary to ensure a sufficient flow per minute for use by the fire department in the event of a fire at the property.
During the report of city officials City Service Safety Director Joe Cappuzzello said that the city had already received 1,000 tons of its total order of 1,600 tons of road salt for 2027 and is due to receive another 200 tons this week. The remaining 400 tons are expected to arrive soon.
Cappuzzello also said that the equipment the city ordered for its new brine pre-treatment system had arrived and was working during tests with water. The system is expected to be fully operational in early December for deployment in the upcoming winter weather season.
Cappuzzello said he hopes the system will help the city to reduce its salt usage by approximately 25% amid soaring salt prices across the state.
During her report Mayor Cyndi Baronzzi Dickey said that the large tree in front of city hall, which the city typically decorates for the holiday season, had been cut back and will be replaced with a new conifer pine soon. She explained that the old tree had been dying and beginning to rot for the last several years, and that while the new tree would be smaller initially, it would grow to the same size as the old tree eventually, and will be safer for city employees when decorating and trimming moving forward.
Other matters approved included a resolution authorizing Dickey to accept a $50,000 grant from the city's electric aggregation program approving TruCut Inc.'s participation in the Economic Growth Initiative Incentive Program as set out in Chapter 187 of the codified ordinances of the city of Salem.
During the report of standing committees City Councilwoman Sara Baer announced that the economic development committee will meet prior to council's next meeting at 5:30 p.m. on Dec. 1, and Councilman Jim Harrington announced that the finance committee will meet at 6 p.m. on the same date.
Council will meet next at 7 p.m. Dec. 1.